Haywood Leisure Centre
15-12-2017
This was a new build site, the equipment installed was Mitsubishi Electric.
On the ground floor 12 Ducted units running of 2 x City multi heat recovery condensing units were installed and on the first floor open plan gym area 10 x ceiling cassette units were installed, all services were on show due to the exposed ceiling layout, which meant the standard of the installation and to be aesthetically pleasing.
This project took 2 months to complete.Visit the eco-ac website for more information on Haywood Leisure Centre